When an event is created based on a planned work shift, the default project for the event can be set to be the work shift's location instead of the person's default project.
Instructions for creating an event based on the planned work shift can be found here.
In project targeting settings you can configurate if events are targeted to a work shift's location or to person's default project.
Configuration can be done either at the Working community level or at a setting group level.
- Select the level where you want to define the settings.
- Select Projects.
- Select the desired setting for 'Target the worktime event to the project of the planned work shift. If "no" is selected, the person's default project is used'.
When defining settings, use the validity function (calendar icon), through which you can activate the setting from a date of your choice.
If setting is set to 'No', Nepton uses the default project set in the person's information page in Employees-section.